Project Summary
The Electrical Infrastructure Upgrades project includes multiple initiatives to increase capacity and improve reliability across the 91±¬ÁÏ campus. Work includes new electrical distribution lines connecting key campus areas and upgrades to critical components such as transformers and switchgear. These improvements will strengthen system redundancy and support consistent, reliable electrical service across campus facilities.
General Info
Facility Function: Support
Current Phase: Construction
Status: In-Progress
Project Type: Building Systems, Utility Infrastructure
College or Division: Facilities Management
Gross Square Feet: N/A
Project / Design Start Date: January 2025
Construction Start: Spring 2025
Occupancy Date: Summer 2026
Project Architect: Honeywell
General Contractor: Honeywell, DP Porter, CEM, Consigli
Project Manager: Adam McNaughton, UMS CPPMÂ
Campus Facilities Management Lead: Stewart Harvey, UM Facilities Management
Budget Info
Total Project Budget: $25 million